The works are finished, the installations run, the handover is signed. And in the first winter it is 19 degrees in one office and 25 in the next. Nobody did a bad job. It is simply that the tuning was never ordered from anyone.
Ask who is paid to tune your building during its first year of operation. If the answer is “the contractor, under the warranty”, then the answer is: nobody. A warranty covers a defect. It does not cover tuning.
What a handover checks, and what it does not
A handover checks that what was ordered has been delivered and that it works. The pump runs, the damper opens, the sensor measures, the alarm comes through. It is necessary, it is contractual, and it says nothing about the question the occupants care about: is the building comfortable, and does it use what was announced?
Between “it works” and “it is tuned” lies a year of work. Project documents almost never provide for it.
The Swiss reference document on the subject says so plainly, and already did in 2002. The Swiss Federal Office of Energy's guide to the optimal operation of complex installations describes a new installation as more or less a prototype, and draws the consequence: as a rule, all these factors call for fine tuning at the start of operation.
A prototype. That is exactly what it is: catalogue equipment, combined for the first time in this configuration, in this building, for these particular occupants. It exists nowhere else.
Why the calculation never comes out right
This is not a flaw in the design. It is a property of calculation.
Sizing works on assumptions: an occupancy, internal gains, uses, a behaviour. The current reference document — Energy optimisation of operation, published in 2021 by the Conference of Cantonal Energy Directors and SwissEnergy — puts it this way: simulations are based on planning assumptions that do not necessarily match how the finished building actually runs. And further on, about the hardest part to predict: user behaviour is extremely difficult to estimate reliably.
Add everything that moved between the building permit and moving in: a change of use, a floor let to someone else, a partition moved, an open-plan office turned into a meeting room. Each of these decisions is legitimate. None of them ever filters down to the tuning of the installations.
The same document records the result, and it explicitly includes new buildings: even new buildings built to energy labels often use considerably more energy than necessary.
The honest figure
It is often said that optimising a building's operation saves 10 to 15 % of its energy. The figure is fair, but its origin should be stated: both federal publications present it as practical experience, with no study behind it.
A few pages further on, the same document publishes what was actually measured in the field: an average saving of 5 % of final energy, climate-corrected. That figure comes from a federal study of some 1,400 buildings.
Five per cent measured on average, ten to fifteen announced from experience. Both appear in the same publication, which does not reconcile them. So we quote both, and we keep the lower one when it comes to committing to anything.
Five per cent, for tuning that requires no hardware, is already a lot. And comfort is not measured in per cent: it is measured in calls to the property manager.
What counts as optimisation, and what does not
The word “optimisation” is used today to sell almost anything, often a piece of equipment. The SIA 2048 technical bulletin draws a clear line: energy optimisation of operation covers measures with a short payback period, as a rule under two years.
It is a very useful criterion for a building owner, because it comes down to a single question: how long before this measure pays for itself? Under two years, it is tuning. Beyond that, it is an investment — perfectly legitimate, but it should not be sold as optimisation.
The timing is fixed too. The 2021 document is explicit: the right moment for an operational optimisation is after the first year of operation. It takes a full year, because a building must have been through a winter, a summer and a mid-season before anything can be said about how it behaves.
| Moment | What is checked | Who pays for it |
|---|---|---|
| Commissioning | the installation works as per contract | the contractor, within its price |
| Handover | what was delivered matches what was ordered | the building owner, through site management |
| First year of operation | the building is tuned for its real occupants, and uses what was announced | nobody, unless it is written down |
What we actually find in the first year
Nothing exotic. Always the same family of things, and hardly ever a breakdown.
Setpoints left at their commissioning values, set high so that nobody complains on handover day — the subject of our article on the heating curve that is too high. Schedules that match the occupancy planned in the project, not the one that actually moved in — see schedules and calendars. Overrides set for a site acceptance and never released. One uncomfortable room compensated for by detuning a whole floor. And meters installed, connected, never read.
Each of these takes a few hours to correct. None of them shows on a supervisor: everything is green, because equipment set too high is not in fault — it does exactly what it was told.
The building ends up tuning itself anyway, on its own, and badly. One occupant opens a window in February. Another brings in a fan heater. The operator puts the ventilation back on permanent run so as to stop getting calls on Monday mornings. Each of them is right within their own remit.
Two years on, the building works — no complaints, and well above its announced consumption. That is the state in which we find most installations: not broken, but balanced around the wrong point.
The six lines to provide for before the works end
- A tuning service for the first year of operation, budgeted just like commissioning — not left to the warranty, which only covers defects.
- A review after the first heating season, with the operator, the contractor and the building owner around the same table, and minutes.
- The data points needed to carry it out: supply and return temperatures, positions of control devices, speeds and power drawn, override states. Without them, the review comes down to impressions — which is what the points list is for.
- Meters read, by use, from the first month — including, and above all, those already installed.
- A named list of active overrides, handed over at acceptance and re-read at the review. A lasting override is not an alarm, so someone has to go and look for it.
- The decision rule in writing: any measure with a payback under two years is tuning and falls within the service; beyond that, it is an investment decided separately.
“An operational optimisation service is provided for in the contract for the first year following commissioning, separate from the warranty and budgeted separately. It includes at least one review after the first heating season, bringing together the building owner, the operator and the contractors concerned, and results in minutes listing the settings changed and the overrides released. The data points needed for this review — supply and return temperatures, positions of control devices, speeds and power drawn, override states — together with the monthly reading of meters by use, are delivered and active from commissioning.”
This service does not appear in a file of its own accord, because it belongs to no trade: the contractor delivered, site management accepted, the operator took over. So we write it in at the point where it costs least, that is, before the tender, and then we carry it out.
We stand on the building owner's side, never on the side of whoever executes: the party that writes a specification cannot be the one that answers the tender it leads to. The aim of a first-year review is not to catch a contractor out. It is to tune a building for the people who work in it, with the people who built it, while they are still around.
A new building is not a finished product, it is a prototype that has just been assembled for the first time. Commissioning proves that it works; handover proves that it complies; nothing in an ordinary file proves that it is tuned. That third line has to be ordered, it has to be budgeted, and it is the cheapest of the three.
wall-i is an independent MCR and BMS engineering practice based in Valais, Switzerland. We write the first-year service into the specification, then we carry it out. A topic you would like us to cover: hello@wall-i.ch